Stalled Public Works Paralyse North West District’s Mega Projects

Date:

Widespread financial, operational, and legal consequences have rippled through the North West District as several major infrastructure projects continue to face severe public works delays.

Chief among these is the long-awaited refurbishment of the Old Maun General Hospital, a facility expected to improve primary healthcare, cut operational expenditures, and relieve intense overcrowding at Letsholathebe II Memorial Hospital.

According to the latest District Development Committee (DDC) report, physical progress remains stubbornly stuck at 90 percent nearly a decade after its July 2017 commencement and long past its original 2018 completion target.

Outstanding works are currently stalled at the Department of Planning and Development, prompting numerous ministerial site visits to map out project delivery strategies. Fortunately, Assistant Minister of Transport and Infrastructure Keoagile Atamelang recently announced that the government has finally secured the necessary funding to finish the hospital works.

A similar bottleneck has hit the construction of the Directorate of Public Prosecutions (DPP) facilities in Maun. Initially slated for final project closure and completion by March 2024, the contract is trapped at 94 percent completion following a string of contractor claims and structural delivery bottlenecks. The DDC report reveals a glimmer of progress, however, noting that outstanding mechanical works have finally been awarded, with onsite operations scheduled to have commenced on August 27, 2026.

Meanwhile, construction on the new Ombudsman Regional Offices in Maun has grounded to a halt at a mere 55 percent physical completion. Initially designed as a swift six-month project that started in October 2019, it was scheduled to open its doors in April 2020.

Ombudsman Advocate Stephen Tiroyakgosing previously revealed that multiple joint interventions with the Ministry of Finance and the Ministry of Transport and Infrastructure have yielded no results. Blaming the Ministry of Transport and Infrastructure for the ongoing stagnation, Tiroyakgosing stressed that his office had secured and budgeted the funds for the project years ago. The DDC report confirms outstanding works remain under the Ministry’s Department of Planning and Development, despite numerous crisis site visits by Assistant Minister Atamelang.

Compounding these delays is an operational crisis at the Maun Centre for Special Education. Although construction on the facility is technically complete, it remains entirely non-functional and closed to the public. Built specifically to support learners with severe-to-profound intellectual and multiple disabilities (SPIMD), the center is crippled by construction defects, poor architectural design, unresolved contract issues, and a total lack of oversight during construction. In response to this operational failure, the development committee has vowed to intervene directly and engage relevant line ministries to rectify the pending defects.

Finally, the district’s critical water infrastructure projects present a deeply mixed picture. Contract 1 of the Maun Water Supply and Sanitation Scheme Phase II, which aims to expand water distribution and wastewater systems across the entire buildable area of Maun, stands at 90 percent completion against a planned 97 percent targets, with progress heavily dragged down by severe cashflow constraints that block material purchases.

Conversely, Contract 2 covering borehole equipping and transmission pipelines is at an advanced 99 percent stage, with only a single borehole awaiting final power connection by the Botswana Power Corporation. While the design and construction of wastewater treatment plants in Maun East and Maun West under Contract 3 are 100 percent complete, the critical upgrading of the Semolo water treatment plant has suffered total collapse. Stuck at a mere 21 percent completion against a planned 70 percent targets, the contract has officially been terminated, forcing the government to actively source additional emergency funds to procure a replacement contractor.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

spot_imgspot_img

Popular

More like this
Related

Botswana’s Young Coders Go Global

23 Maun students represent Botswana in a 50-country coding...

Boko Urges MPs To Deliver Meaningful Change For Batswana

President calls for systematic parliamentary oversight, early public consultation,...

WHO Calls For Domestic Malaria Funding Amid Case Spike

World Health Organisation (WHO) Director-General Dr Tedros Adhanom Ghebreyesus...

Botswana P413 Million IFAD Loan To Commercialise Agriculture

The funding boosts smallstock and poultry enterprises across 20...
Verified by MonsterInsights