Mohembo Bridge: Will June Deadline Be Met?

Date:

One of Ngamiland major projects that is expected to transform the livelihoods of communities in the area, The Mohembo Bridge is finally expected to open for traffic during the second week of June after missing numerous deadlines.

The completion dates for the project have been moved four times from the initial completion date of August 2021 which was later moved to October of the same year. This was later moved, without any specific date to before the end of the year

The bridge, according to President Mokgweetsi Masisi’s state of the nation address in 2021, was supposed to have been opened for use during the month of April, and the deadline was not met. This has left many stakeholders sceptical about the new deadline.

Responding to this publication’s questionnaire regarding the persistent delays early this year, Department of Roads Acting Director Motsayalere Basuti acknowledged that the contractor has indeed not met his deadline of completing the project on time. He pointed that in some instances one of the contributing factors to the delay is the unsatisfactory performance by the contractor.

The project is undertaken by Italy’s Itinera and Cimolai Joint Venture as the Contractor and CPP Botswana as the supervising Consultant.

“It is true that the contractor has not met his deadline of completing the project on time. However, the contractor’s lack of performance will be addressed under the contract signed,” Basuti noted. The Acting Director however did not go on explain how the issue will be concluded.

Basuti then confirmed that the contractor’s plan was have the bridge open for traffic in April this year. The project commenced in November 8, 2016 with an original completion date of July 7 2019.

He also indicated then, that as at the end of November last year the overall progress of the project was at 99.2%.

“Progress for the bridge works was at 99.3%, for electrical works was at 95.5%, for road works it was also at 95.5%, for erosion protection works was at 85% while for the removal of the temporary platform the progress was standing at 90%,” Basuti revealed.

Meanwhile in his speech at the ongoing Okavango Sub-district council meeting this week, Chairman Mpoke Karapo, highlighted in passing that the project is at 99.57% complete and is expected to be open to traffic by the second week of June 2022.  

Unlike in his previous speeches, Karapo did not elaborate on the cause for the delays.

Regarding the Nokaneng – Gumare asphalt overlay, Karapo revealed that the contractor has since abandoned the site and had promised to be back on site by April 19, but has not kept his promise.  “But as stated in the last speech all due processes are being considered,” he said.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

spot_imgspot_img

Popular

More like this
Related

Botswana’s Young Coders Go Global

23 Maun students represent Botswana in a 50-country coding...

Boko Urges MPs To Deliver Meaningful Change For Batswana

President calls for systematic parliamentary oversight, early public consultation,...

WHO Calls For Domestic Malaria Funding Amid Case Spike

World Health Organisation (WHO) Director-General Dr Tedros Adhanom Ghebreyesus...

Botswana P413 Million IFAD Loan To Commercialise Agriculture

The funding boosts smallstock and poultry enterprises across 20...
Verified by MonsterInsights