Residents of Okavango Sub District will have to wait a little longer before they can start using the newly constructed iconic Mohembo Bridge. This is because its completion date has once again been delayed with no date as to when it will be open to use by the public.
In the meantime, the residents will continue to bear the burden of crossing the mighty Okavango River using the unreliable ferry which has consistent breakdowns.
Having postponed its completion dates three times already, the multi-million Pula project was initially anticipated to be completed August 2021 this year. Its completion date was however later moved forward to October the same year.
When it was expected that President Mokgweetsi Masisi would in his State of the Nation address recently announce the completion date and possibly its opening date, he instead indicated that the bridge will be open for public use by the end of this year.
Addressing the Okavango Sub District Council meeting this week, its Chairman, Mpoke Karapo reiterated that construction of the bridge is still ongoing noting that the contractor has failed to meet the previous revised completion date of October 2021.
The cumulative progress achieved is 99% against cumulative planned progress of 100% as at the end of October 2021.
“The overall progress status of the project is 1.7 weeks behind as per contractor planned completion date of 20th October 2021,” he revealed. The major components of the bridge according to the Council Chairman are almost complete with the remaining works being installation of hand rails, final stay cables tensioning, painting of concreate barriers, electrical works, asphalt surfacing and road markings.
Meanwhile Karapo has appreciated that the opening of the bridge to the public is expected to greatly ease the movement of goods and people across the Okavango River who are currently relying on the ferry at Mohembo which is always affected by breakdowns.
Regarding other ongoing major projects in the district Karapo indicated that the Asphalt Overlay of Nokaneng – Gumare Road (37km) was awarded to Evergreen Contractors (Pty) Ltd at a contract sum of P53, 486, 619.20.
“The initial project is currently running outside the contract period by 12-months. The overall process of the project to date remains standing at 50% against the planned 100%. The contractor resumed paving activities on site from the 12th of October 2021 but currently there are no activities going on,” he revealed.
According to Karapo, the contractor cited cash flow problems but has since assured to resume surfacing activities after receiving his pending payments. The contractor has however been advised to prioritize surfacing reconstruction sections since the country is approaching raining season. Nonetheless as of October 30, 2021 only 3.25km out of 7.5km of reconstructed sections were paved.
On a positive note, Karapo indicated that the shoulder reinstatement and Asphalt overlay tender for the 170 kilometer Gumare-Mohembo road has been planned for this financial year. Tenders are said to be at the adjudication stage. The works have been allocated a total of P170, 000,000.00. Karapo noted that the road is currently in a bad state as it has exceeded its design life span.
“The road remains impassable and has caused major inconveniences to road users,” he lamented.